MAJOR WATER SECTOR PROJECTS UNDER IMPLEMENTATION IN PAKISTAN
Project Location App. Cost
(Rs. in million)
Live Storage Irrigated Area
(Acres)
Status
Basha Dam (Dam Part) Khyber Pakhtunkhwa & Gilgit Baltistan 510,000 6.40 At initial stage
Gomal Zam Dam Khyber Pakhtunkhwa 20,626 0.892 MAF 191,139 (17.4 MW Power Gen.) Completed & Operational
Kachhi Canal (Phase-I) Balochistan 80,352 72,000 Physically completed. (Phase-I)
Darawat Dam Sindh 9,300 89,192 (Ac.Ft) 25,000 (0.30 MW Power Gen.) Physically completed
NaiGaj Dam Sindh 26,236 160,000 (Ac.Ft) 28,800 (4.2 MW Power Gen.) 50 % Physical works completed
KurramTangi Dam (Phase-I,Kaitu Weir) Khyber Pakhtunkhwa 21,059 0.90 MAF 84,380 New
278,000 Existing (18.9 MW Power Gen.)
17% works completed.
Works at initial stage
Naulong Dam Balochistan 18,027 0.20 MAF 47,000 (4.4 MW Power Gen.) Feasibility & Detailed Engn.
Design completed
Works on dam not yet started.
Mohmand Dam FATA Mohmand Agency 114,285 0.676 MAF 16,737 (800 MW Power Gen.) Feasibility & Detailed Engn.
Design completed
Formulation of PC-I & Financial mechanism are in progress
Right Bank Outfall Drain (RBOD)
RBOD-I
RBOD-II
RBOD-III
Sindh
Sindh
Balochistan
17,505
61,985
10,804
ROBD-II will help to dispose
3,520 cusecs of drainage effluent into Sea received from RBOD-I & III
82% completed
63% completed
74 % completed