MAJOR WATER SECTOR PROJECTS UNDER IMPLEMENTATION IN PAKISTAN
ProjectLocationApp. Cost
(Rs. in million)
Live StorageIrrigated Area
(Acres)
Status
Basha Dam (Dam Part)Khyber Pakhtunkhwa & Gilgit Baltistan510,0006.40At initial stage
Gomal Zam DamKhyber Pakhtunkhwa20,6260.892 MAF191,139 (17.4 MW Power Gen.)Completed & Operational
Kachhi Canal (Phase-I)Balochistan80,35272,000Physically completed. (Phase-I)
Darawat DamSindh9,30089,192 (Ac.Ft)25,000 (0.30 MW Power Gen.)Physically completed
NaiGaj DamSindh26,236160,000 (Ac.Ft)28,800 (4.2 MW Power Gen.)50 % Physical works completed
KurramTangi Dam (Phase-I,Kaitu Weir)Khyber Pakhtunkhwa21,0590.90 MAF84,380 New
278,000 Existing (18.9 MW Power Gen.)
17% works completed.
Works at initial stage
Naulong DamBalochistan18,0270.20 MAF47,000 (4.4 MW Power Gen.)Feasibility & Detailed Engn.
Design completed
Works on dam not yet started.
Mohmand DamFATA Mohmand Agency114,2850.676 MAF16,737 (800 MW Power Gen.)Feasibility & Detailed Engn.
Design completed
Formulation of PC-I & Financial mechanism are in progress
Right Bank Outfall Drain (RBOD)
RBOD-I
RBOD-II
RBOD-III
Sindh
Sindh
Balochistan
17,505
61,985
10,804
ROBD-II will help to dispose
3,520 cusecs of drainage effluent into Sea received from RBOD-I & III
82% completed
63% completed
74 % completed